Abbott Orders Strict Penalties for Data Centers Failing Texas Water Surveys

Abbott asked the Texas Water Development Board to provide an update on reporting compliance and enforcement by Oct. 14, while the board said it does not track how many fines have been issued and has previously maintained that, as a non-regulatory agency, it lacks authority to prosecute violations.
The water board has requested water-use information from data centers annually since 2020, with the survey process seeking monthly consumption data to support the state water plan.
Abbott’s broader data-center oversight effort includes a pause on approvals until regulators complete their audit, and ERCOT is expected to survey more than 400 data centers as part of that review.
The August 3 audit order applies to data centers that advance through ERCOT’s interconnection process, linking water-reporting scrutiny to whether projects receive approval to connect to the Texas grid.
The reporting requirement is not limited to data centers: it applies to recipients of TWDB surveys among major water users, and Abbott’s directive says the agency should notify TCEQ when a noncompliant facility may be disqualified from obtaining a permit under Chapter 11 of the Texas Water Code.
Texas Gov. Greg Abbott has ordered state regulators to penalize data centers that fail to report their water use, with noncompliant facilities facing Class C misdemeanor charges and losing eligibility for key environmental permits. MySanAntonio reports only about 28% of data centers responded to recent mandatory surveys, leaving the state unable to plan for future water demand. The directive applies to the 2025 survey due March 1.
Data centers currently use less than 1% of Texas water statewide, but Newsweek notes researchers project their share could jump to 3%–9% by 2040. Abbott also ordered a broader audit of data centers' water consumption, cooling systems, and grid connections, linking compliance to approval for connecting to the Texas electric grid.
The Texas Water Development Board has sought water-use data from data centers annually since 2020 to support state planning. However, NewOrleansCityBusiness reports the board itself admitted it lacks authority to prosecute violations, as it functions as a non-regulatory agency. The board has not tracked how many fines have been issued. Abbott asked for a compliance update by October 14.
Enforcement may depend on county and district attorneys taking action. Abbott's directive tells the water board to notify the Texas Commission on Environmental Quality when noncompliant facilities should lose permit eligibility under state water code. The challenge: translating penalties into actual prosecution remains unclear.
Abbott paused approvals for data centers pending completion of the state audit, GVWire reports. ERCOT, which manages Texas's power grid, expects to survey more than 400 data centers as part of the review. The August 3 audit order links water-reporting compliance directly to whether projects win approval to connect to the grid.
This creates pressure: data centers cannot advance without proving water responsibility. Abbott ordered coordination between the water board, the Public Utility Commission, and ERCOT to examine data centers' water sources and cooling technologies. The audit aims to understand how rapid data center growth could strain both water and electricity infrastructure.
SouthTexasNews notes data centers are not the only water users subject to reporting. The directive applies to all recipients of water-use surveys among major consumers statewide. But data centers face unique pressure because their rapid expansion threatens to reshape Texas water budgets within two decades.
With only 28% response rates, the state cannot forecast demand or plan infrastructure upgrades. Abbott's enforcement order signals that voluntary compliance has failed. Without mandatory disclosure, Texas cannot prepare for either drought or growth. The penalties aim to close that information gap.