Algoma Steel resumes production following an unplanned turbine outage at its power facility.

Algoma initially estimated the Lake Superior Power turbine outage would last no more than 21 days, with production continuing under interim arrangements during that period.
Algoma is under a long-term service agreement with GE Vernova to mobilize and commission a contracted spare turbine at Lake Superior Power as part of restoring normal generating capacity.
One turbine unit at Lake Superior Power detected an abnormal condition and was automatically taken offline, while the remaining units were not affected.
Algoma resumed electric arc furnace production on August 29, 2026, despite the damaged turbine remaining unavailable.
The company's stock rose about 4.8% following the update that EAF production had resumed amid the power outage issues.
Algoma Steel has resumed electric arc furnace production in Sault Ste. Marie, Ontario, after an unplanned turbine outage at its Lake Superior Power facility forced a temporary shutdown. Mining Weekly reported that the company restarted operations on August 29 under interim arrangements with the provincial grid operator, allowing steelmaking to continue while the damaged turbine remains offline.
The company is pursuing multiple paths to restore full generating capacity, including working with GE Vernova to mobilize a spare turbine. Seeking Alpha noted that Algoma's stock rose about 4.8% following the update, as investors responded positively to the maintained production despite the power supply disruption.
One turbine unit at Lake Superior Power detected an abnormal condition and was automatically taken offline on August 17. CTV News reported that the equipment failure forced Algoma to suspend steel production temporarily. The remaining turbine units were not affected by the fault, limiting the scope of the outage to one generator.
Algoma initially estimated the outage would last no more than 21 days. Northern Ontario Business noted that the company had made alternative arrangements to keep operations running during that window. Working with the IESO, Algoma secured interim operating parameters to maintain production levels.
Algoma is under a long-term service agreement with GE Vernova to mobilize and commission a contracted spare turbine. Recycling Today reported that the company is pursuing this option as one path to restoring normal generating capacity quickly. The timeline for deployment depends on logistics and commissioning schedules.
The company is also exploring turbine repair as an alternative solution. By pursuing both repair and replacement options in parallel, Algoma aims to determine the most effective path forward. The company has not yet announced which approach will ultimately be selected or when full capacity will be restored.
The IESO reviewed Algoma's situation and approved interim operating arrangements to prevent disruption to the provincial electricity grid. Northern Ontario Business reported that the grid operator is coordinating upcoming outages at other facilities to minimize cumulative strain. Maintaining grid reliability was central to allowing Algoma to resume operations under temporary parameters.
Algoma says production and shipments are currently within the interim parameters approved by regulators. The company continues to assess potential impacts as it advances planned power-system mitigations. This situation underscores how steelmaking operations depend on stable, reliable power supply and close coordination with grid operators.