No trains at Birmingham New Street over Christmas

Network Rail said Birmingham New Street is “at the heart of the rail network,” supporting millions of local, regional and national journeys each year, underscoring the station’s importance despite the Christmas timing of the closure.
The renewal will cover complex overhead-line sections on the approaches to and through Birmingham New Street, including the equipment that keeps electric trains running—not just wiring within the station itself.
Passengers travelling from Northampton toward Birmingham are specifically warned that the five-day closure may affect their Christmas journeys and could require replacement or local buses.
Network Rail said it had worked with train operators and other partners to reduce the disruption caused by the first phase of the project.
Birmingham New Street station will close to all train services from December 24 to 28 as Network Rail begins a £13 million upgrade of aging overhead power lines. The work replaces equipment mostly installed in the 1960s and marks the first phase of a three-year modernization program. Passengers face longer journeys and possible rail-replacement or local buses during the five-day closure.
The station itself will remain open, keeping shops, toilets and assisted-travel facilities available. Network Rail said Birmingham New Street sits "at the heart of the rail network," handling millions of local, regional and national journeys yearly. Detailed timetables and travel information will be released from early October.
The overhead lines feeding power to electric trains date back roughly 60 years. Network Rail chose Christmas because it offers a concentrated five-day window with reduced passenger demand. Waiting until summer or spring would stretch disruption across many more days. The equipment needs replacement now to avoid frequent failures that disrupt commuters year-round.
This Christmas closure is just the start. Network Rail plans two more major upgrades in 2027 and 2028, each likely causing similar five-day station closures. The full three-year program aims to replace the entire aging overhead-line system on approaches to and through Birmingham New Street. Once complete, reliability should improve significantly for the millions using the station annually.
Passengers traveling from Northampton toward Birmingham face the biggest impact. Network Rail warns that rail-replacement buses or local buses will replace train services during the closure. Journey times will increase significantly. The agency worked with train operators to reduce disruption where possible, but alternatives remain limited for the five-day period.
Early October will bring comprehensive travel information and updated timetables. Passengers planning Christmas trips should check with their train operator as soon as details are released. The station's facilities—shops, toilets and assistance services—will operate normally to support travelers using replacement transport.